Trident Park EfW, Cardiff
Standing Seam Roof and Wall Cladding with Polycarbonate Features and Paroc Perimeter Cladding
SCF were involved in the installation and site management of the full roofing and cladding package at Trident Park EfW. The project was extremely complex due to the building curving on plan as well as in section. The standing seam cladding was installed at 45deg. and was a huge logistical challenge for the building. The Roof Standing Seam was a complex task due to the pitch of the roof and required the installers to use specialist climbing kit to be able to walk up to the ridge point.
Products
Euroclad ES400 Roof Sheets
Euroclad ES400 Wall Sheets
Rodeca Polycarbonate Wall Cladding
Paroc Wall Panels