Pendleton Beech and Holm Court, Salford
Remediation of Building Structure and Installation of New Fire Safe Cladding
SCF were approached to assist in the cladding remediation works to the Pendleton Estate, there are 9no. properties as part of the estate, SCF were initially involved in the cost planning, design and construction of 2 of the properties but are hoping to secure further works on the site as the works to Beech and Holm conclude in early 2025.
SCF were provided with a comprehensive set of Employers Requirements (ER's) for the project, including indicative design calculations and drawings and existing building survey information. With this information we designed the cladding and substructure requirements from our facade engineers calculations and the indicative panel information confirmed within the ER's.